As a minimum the following shall be observed and recorded at 25 50 80 and 100 stepped load during testing of diesel generators on site.
Generator load bank testing procedure.
If a generator fails the monthly test it should be operated under a load supplied by a load bank i e.
Transfer all manual or automatic transfer switches to the emergency source.
Check all fluids level in the generator.
6 4 4 1 1 2 specifies that the 10 second criterion does not apply during the monthly testing of the generator.
During this two hour period the unit should be operated as follows.
At 50 of the nameplate kilowatt rating for 30 minutes.
The recommended procedure to follow for the load bank test would be to start and run the generator until the water temperature stabilizes.
Step load the generator with the load bank until the desired load is reached.
Our test procedures include load test generator set for a minimum of 1 or 2 or 4 consecutive hours.
O engine exhaust temperature during test if applicable p kw load under test q identification of unsatisfactory conditions and corrective action taken including parts replaced note.
Duration of actual test varies based on type of test nfpa 110 and customer preference.
Standard load bank testing procedure the following is the basic step by step procedure for performing load bank testing on a generator set by utilizing a portable resistive load bank unit.
Make sure that the fuel tank is full the oil level is correct and the radiator or coolant tank is full if it is a water cooled generator.
Start the generator and allow it to reach the normal temperature.
1 apply load in steps used for generator sizing design consultant specify.
These are some of the steps to test a load bank testing.
When combining both tests for diesel powered eps the first three hours of the test is required to be not less than 30 of the emergency generator nameplate kw rating or the minimum exhaust gas temperature.
Run at 80 of rating with 100 verification or as described in service agreement.
Transfer all manual or automatic transfer switches to the emergency source.
The last hour cannot be less than 75 of the emergency generator nameplate kw rating for a total of 4 continuous hours.
Start and run the generator until the water temperature stabilizes.
At 25 of the nameplate kilowatt rating for 30 minutes.
Perform a stepped load bank test.
1 volts and amps on each phase voltage unbalance between phases shall.
The recommended procedure to follow for the load bank test would be to.
Load bank testing is a standard part of our preventative maintenance service agreements and is accomplished without any interruption to facility operations.
The generator is then step loaded with the load bank until the desired load level is reached.